01. October 2023
Journal Geomechanics and Tunnelling 05/23 published
Cover picture:
The new Tauernmoos power plant is an important cornerstone for the supply of traction power from hydropower. The project includes the construction of an underground powerhouse with a length of 73 m, a width of 25 m, and a height of 40 m. In addition, 11.5 km of tunnels and galleries were excavated for the project, for which DSI Austria supplied the complete range of ground support means.
(photo DSI Underground Austria)
Table of Contents Journal Geomechanics and Tunnelling 05/23
- General Rules
- Eurocode and the basis of structural and geotechnical design
- Ground properties
- Geotechnical structures: anchors, rock bolts soil nails, and groundwater control
- Geotechnical structures: slopes, spread foundations and retaining structures
- Perspectives on the evolution to the 2035 third generation of Eurocode